Upcoming work

November 2023

Bituminous paving has been completed on the southbound lanes of PTH 10 and the facility is now fully open for all traffic lanes.

The demolition of the existing Daly Overpass bridge will continue through the fall and winter, with overall project completion planned for summer 2024.

September 2023

July 2022

May 2022

April 2022

February 2022

  • Construction activities, including piling, sewer and water works, will commence February 22, 2022.
  • A full road closure of McDonald/Stickney Avenue between 17th and 19th Street North is anticipated until July 1, 2022
  • Detours will be in place as shown on the map of closure at McDonald / Stickney (PDF)
  • Manitoba Transportation and Infrastructure has awarded the contract for the construction of the Daly Overpass to Coco Paving (Canada) Inc. Construction work is set to begin with equipment mobilizing to the site and construction detours will be established in the next few weeks. Two lanes of traffic (one in each direction) will be maintained throughout the project period, with a few minor exceptions for brief periods. Further updates will be provided in advance of changes in traffic accommodation during construction.

June 2021

  • Completion of building demo and site clean-up

May 2021

  • The east end of the Homefarms building (approximately 24 meters or 80 feet in length) will be entirely demolished. The remaining portion, including Cree Nation Child and Family Caring Agency and the YWI Immigration Services, will not be demolished. These agencies will be open during demolition.

April 2021

  • Exterior demolition of the Kullberg’s building.

New Daly Overpass on PTH 10 in Brandon

Project description

The 3-year project involves the construction of a new four-lane bridge with a separate pedestrian and active transportation bridge. The design will also include a new on and off ramps to connect 18th Street with Pacific Avenue, new pathways, sidewalk and pavement upgrades. In addition to the extensive bridge and road construction, the project requires demolition of several properties including the over a 100 year-old Kullberg’s building, as well as relocation of multiple public and municipal utilities.

Daly Overpass Project (PTH 10 - Brandon) (PDF, 2.8 MB)

Project updates

Manitoba Transportation and Infrastructure (MTI) is currently tendering the replacement of the 58-year old Daly Overpass in Brandon. The Daly Overpass is an existing bridge that crosses the CP Mainline and forms a critical component of the road system in Brandon and the greater Brandon region. Construction of the new overpass will run approximately from November 2021 to the end of 2023, with the final finishing touches taking place in Summer 2024. Traffic will be permitted on the overpass using one lane in each direction throughout the life of the project, with short, temporary full street closures on occasion. MI will continue to update the public on project status and traffic control through MI website and newsletters.


3D Renderings of Completed Project

NE looking SW over Ped area
NE looking SW over Ped area
SE looking NW over Bridges SE looking NW over Bridges
SW looking NE over Bridges SW looking NE over Bridges
View from Ped Path (bottom of stairs) View from Ped Path (bottom of stairs)
Wheat Sheaths Wheat Sheaths

 

Contact

For inquiries, please contact us at dalyoverpass@gov.mb.ca.


Photo updates

Manitoba Transportation and Infrastructure will continue to provide photo updates throughout the construction period.

 

June 2023



 

 

May 2023





 

 

September 2022



 

 

Homefarms Demolition

Homefarms demolition - May 19, 2021
Homefarms Demo - May 19th Homefarms Demo view 2 - May 19th 2021
 

 

HomeFarms demolition - May 18, 2021
HomeFarms demolition - May 18, 2021, view 1 Honveyfarms demolition view 2 - May 18, 2021
 

 

Demolition on the Homefarm building has started
Demolition on the Homefarm building has started
 

 

Kullberg's demolition is nearing completion
Kullberg's demolition is nearing completion Kullberg's demolition is nearing completion view 2 Kullberg's demolition is nearing completion view 3

 

April 15, 19 and 21, 2021 - Construction continues
April 15, 19 and 21, 2021 - Construction continues April 15, 19 and 21, 2021 - Construction continues view 2 April 15, 19 and 21, 2021 - Construction continues view 3
 

 

April 7, 2021 - Demolition started on the office portion of the Kullberg’s building.
Project Update – April 7, 2021 – Demolition started on the office portion of the Kullberg’s building. Project Update – April 7, 2021 – Demolition started on the office portion of the Kullberg’s building - view 2
Project Update – April 7, 2021 – Demolition started on the office portion of the Kullberg’s building - view 3 Project Update – April 7, 2021 – Demolition started on the office portion of the Kullberg’s building - view 4
 

 

 

Project Update - February 24, 2021 – Wheat Kings signs coming down
Project Update - February 24, 2021 – Wheat Kings signs coming down Project Update - February 24, 2021 – Wheat Kings signs coming down - view 2